Donau Carbon
Sheffield.
Man Hours: 25,000.
Fabricom Contracting Limited carried out the construction of a new Solvent Recovery Plant at the Polestar printing works in Sheffield. The scope of work included the erection of:
275,000Kg - Vessels (Including 12 off 17t Absorbers)
31,000Kg - Mechanical Equipment, Pumps, Etc.
45,000Kg - Structural Steelwork
110,000Kg - Piping (Including fabrication and testing)
The project was initially delayed due to civil activities; however Fabricom submitted and subsequently achieved an accelerated recovery program from 12 weeks to 9 weeks on site, to bring the project in on time with no lost time injuries.